Supplied by Stephenson Equipment, 84 Lumber and its framing partner, R. R. Miller Construction used two Potain self-erecting tower cranes— the Igo T 130 and Igo T 99— to overcome tight-site logistics and keep the project moving without having to reposition a crane mid-construction. took place from November 2024 through mid-June 2025, the team behind the project had to find a way to lift heavy prefabricated materials efficiently without disrupting the surrounding neighborhood. For 84 Lumber, which oversaw the lifting operations through its Installed Sales Division, the answer came in the form of two Potain self-erecting tower cranes— the Igo T 130 and Igo T 99. Together, these cranes made it possible to overcome tight-site logistics and keep the project moving without having to reposition a crane mid-construction.
“ The T 130 was brought in first, followed by the addition of a Potain Igo T 99 to support the later phases of construction,” explained Steven Rider, commercial install manager at 84 Lumber.“ This dual-crane